Published Date: 05 May 2015

Sectors:
  • Electricity & Gas Icon
    Electricity & Gas

Implementation of Group Processing – Move to Construction Phase

The CER has today, 5 May 2015, published a  Decision Paper on Implementation of Group Processing: Move to Construction Phase.
CER has approved a ruleset developed by the SOs (EirGrid and ESBN) following consultation on the approach to a range of scenarios as projects move towards construction phase (Group Processing connection policy). CER’s decision paper and a recommendations paper prepared by the SOs has now been published. The SOs’ paper includes a summary of the responses to the consultation and the approved ruleset. 
For further information, please contact Paul Brandon at pbrandon@cer.ie. 
Contact Email:
distribution@cer.ie

Round

2014

Document Icon

CER 14432 Implementation of Group Processing - Move to construction