Published Date: 06 Mar 2018

Sectors:
  • Electricity & Gas Icon
    Electricity & Gas

Decision on FCA Common Grid Model Methodology

On 05 March 2018, the CRU notified EirGrid, as the licenced TSO in Ireland, of its decision on the Common Grid Model Methodology, submitted in accordance with Article 18 of EU Commission Regulation 2016/1719, establishing a guideline on Forward Capacity Allocation (FCA). In line with the all Regulatory Authorities agreement and in line with Article 4 of the FCA Regulation, the CRU has requested an amendment to the all TSO proposal on the methodology. The rationale for this decision (the Request for Amendment) is included in the All Regulatory Agreement on CGMM which can be found alongside the CRU decision letter.

Round 1