The Connection Offer Policy and Process (COPP) Paper was approved by the CER in May 2011 (CER/11/093). Since then, the CER has issued a number of clarifications and amendments relating to COPP. Details of these clarifications and amendments are covered in various publications, listed in the table below.
This information note is a single point of reference for these publications. It provides a high level summary of the amendments and clarifications, and links them to the relevant documents.
CER/11/093
|
Connection Offer
Policy & Process (COPP)
|
Amendments and
clarifications:
|
Treatment of
Temporary Connections in Tie-Break Situations
|
SEM-11-105
|
Treatment of
Price Taking Generation in Tie Breaks in Dispatch in the Single Electricity
Market and Associated Issues
|
SEM-12-018
|
SEM Committee
Communication of 29 March 2012
|
SEM-13-010
|
Treatment of
Curtailment in Tie-break situations
|
SEM-13-011
|
TSOs Definition
of Curtailment and Constraint, version 1.0
|
SEM-13-012
|
Constraint
Groups arising from SEM-11-105
|
Transmission
Connection Agreements and Use of System Agreements
|
CER/09/138
|
Electricity
Network Connection Policy
|
CER/13/145
|
Transmission
Connection Agreements and UoS Agreements
|
MEC Security
|
CER/09/138
|
Electricity
Network Connection Policy
|
CER/16/165
|
MEC Security
Policy Amendments
|
Installed Capacity
Cap
|
CER/14/047
|
Installed
Capacity Cap
|
Projects Moving
to Construction Phase
|
CER/15/098A
|
Implementation
of Group Processing – Move to Construction Phase
|
CER/15/098B
|
System Operator
Recommendation following Consultation Paper CER/14/432 – Implementation of
Group Processing – Move to construction phase
|
Treatment of FSP
after Splits, Mergers, Relocations and Reductions of MEC
|
CER/09/138
|
Electricity
Network Connection Policy
|
CER/11/083
|
First Stage
Payments on acceptance of a Connection Offer to the Electricity Network
|