Published Date: 03 Sep 2021

Sectors:
  • Electricity & Gas Icon
    Electricity & Gas

Ireland Region Level 1 Locational Constraints for the 2025/26 T-4 Capacity Auction

The CRU is today, 3 Sept 2021, publishing letters which it issued to EirGrid and ESBN, directing them to give a grid connection offer to any applicant located in the Ireland Level 1 Locational Capacity Constraint Area, that is successful in the T-4 Capacity Auction for 2025/2026, taking into account certain requirements and considerations.

These letters are being issued by the CRU, having considered the risk of capacity shortfall over the coming years and the recent terminations of capacity contracts in Ireland.

Contact Email:
Electricityconnectionpolicy@cru.ie