The CRU has today, 14 May 2018, published its decision to approve the amended TSO proposal for day ahead and intraday arrangements concerning more than one Nominated Electricity Market Operator (NEMO) in the SEM Bidding Zone in accordance with Article 45 and 57 of Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a Guideline on Capacity Allocation and Congestion Management.
On 7 September 2017, the CRU received a multi-NEMO arrangements (MNA) proposal from the TSOs (EirGrid and SONI) outlining the different MNA models applied by some Member States across Europe. These proposals were subsequently consulted on with the CRU publishing a decision letter on the 9 January 2018 requesting that the proposal be amended to recommend an arrangement to be implemented in the I-SEM.
On 13 March 2018, the TSOs submitted an amended proposal detailing multi-NEMO arrangements for both single day ahead coupling and single intraday coupling. These sought to reflect MNA developments taking place in Europe.
The attached letter sets out the CRU’s decision to approve the amended TSO proposal for day ahead and intraday arrangements concerning more than one Nominated Electricity Market Operator (NEMO) in the SEM Bidding Zone
Published Date: 14 May 2018
Sectors:
Information Note on Arrangements concerning more than one NEMO in one bidding zone
2018
Decision on the amended proposal for Day ahead and Intraday Arrangements concerning more than one Nominated Electricity Market Operator (NEMO) in the SEM bidding zone
Round
2018
Viridian_response_to_MNA_Consultation
2018
Nord_Pool_response_to_MNA_Consultation
2018
Bord_Gais_Energy_response_to_MNA_Consultation
2018
Decision on the proposal for Day ahead and Intraday Arrangements concerning more than one Nominated Electricity Market Operator (NEMO) in the SEM bidding zone
2017
CER17056 Annex 2 CER Request for Proposal to EirGrid
2017
CER17055 Annex 1 CER Response to Nord Pool's Notice
2017